Question d’entretien chez Daewoo Engineering

How to close packages

Réponses aux questions d'entretien

Utilisateur anonyme

5 sept. 2017

Received packages, Line checking, Story of fit up reports, Welding reports, NDE reports and Punch reports...

Utilisateur anonyme

6 sept. 2017

Well, i'll assume we are talking about piping test packages in here...Once we receive the package the line will be check,soon a punchlist will come out,indicating those balance work to be done before and after testing. Say for example, a welded joint balance or a temporary gasket,all missing accessories down to the smallest one..