Describe the change order process.

Réponse à la question d'entretien

Utilisateur anonyme

11 févr. 2019

When contract documents don't provide enough or the correct information, the contractor will send an RFI to the consultant. If there needs to be a change to the design, it is issued in a CCN. Once the work is priced, the contractor will submit a quote to the owner/consultant, if approved, a change order is issued and the work proceeds as per the CCN.